August’16 Update

final_logo_artwork


Super Structure Complete


We are pleased to inform on our progress.

  • We have completed the 11th floor. With this super structure is completed.
  • Brick work in 9th floor is in progress.
  • Internal electrical & plumbing works started in 6th floor.

July’16 Update

final_logo_artwork


We are pleased to inform on our progress.

  • We have completed the 9th floor and 10th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 6th floor is in progress.
  • Internal electrical & plumbing works started in 3rd floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.

June’16 Update

Last month’s progress has been the following:

  • We have completed the 8th floor and 9th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 5th floor is in progress.
  • Internal electrical & plumbing works started in 1st floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.