Nov’16 Update

final_logo_artwork


We are please to report on our progress. Details are listed below

  • Super structureCompleted
  • Brickwork Completed
  • Internal Plumbing and Electrical conduiting Completed
  • Internal Plastering – 80% completed (at 9th Floor)
  • External Plastering– 70% completed
  • Flat Flooring – 30% Completed(at 3rd Floor)
  • Corridor/Staircase Flooring – Just started
  • Internal/ExternalPainting – Just started

With this progress we are confident of flats handover for interior works may begin in April 2017 instead of June 2017.

goldenlotus-site-photo2 goldenlotus-site-photo1

Tile Catalogue

Select Tiles for your home today

We customise the interiors of your Upscale home to meet your needs and reflect your sensibilities. In this pursuit, we have created a tile catalogue with various options available for your home. Please send us your choices by filling up the attached form below. Use the accompanying guide for visualisation of the tile options.


DOWNLOAD HERE \ GUIDE \ FORM


HIGH RES PRINT VERSION HERE: FORM | GUIDE

LAST DATE: 29 AUGUST 2016

Screen Shot 2016-08-22 at 10.56.50 AM

Smart Pools

space


Revolutionary Technology – Like a real river flow

As you are already aware your house is being provided with American Standard make sanitary ware, Grohe make Faucets, Schindler make fully automatic machine room less & gear less lifts, Honeywell electrical equipment, USB chargers, etc…

In continuation of our relentless pursuit to provide the latest and best technology in your flat/ complex, this time we have decided to go with Smart swimming pools (Separate for Adults and Children)  ‘SMARTPOOLS’ the only green certified pool product in the world !!!

The goal of this change is to create a richer experience, super hygiene, non-cumbersome & cost effective maintenance and suitable for all age groups from beginners to professionals.

VISIT WEBSITE

 

July’16 Update

final_logo_artwork


We are pleased to inform on our progress.

  • We have completed the 9th floor and 10th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 6th floor is in progress.
  • Internal electrical & plumbing works started in 3rd floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.

June’16 Update

Last month’s progress has been the following:

  • We have completed the 8th floor and 9th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 5th floor is in progress.
  • Internal electrical & plumbing works started in 1st floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.

Hassle-free Charging…

As a testimony to our relentless pursuit of delivering the richest experience, we are adding unique “USB interface wall sockets” to your living and

master bedroom. This will ensure you can charge all your digital gadgets such as mobile phones, tablets, music players etc effortlessly.

“We are committed to crafting a wholesome living experience”
 USB INTERFACE WALL SOCKET

1373196482