August’16 Update

final_logo_artwork


Super Structure Complete


We are pleased to inform on our progress.

  • We have completed the 11th floor. With this super structure is completed.
  • Brick work in 9th floor is in progress.
  • Internal electrical & plumbing works started in 6th floor.

Smart Pools

space


Revolutionary Technology – Like a real river flow

As you are already aware your house is being provided with American Standard make sanitary ware, Grohe make Faucets, Schindler make fully automatic machine room less & gear less lifts, Honeywell electrical equipment, USB chargers, etc…

In continuation of our relentless pursuit to provide the latest and best technology in your flat/ complex, this time we have decided to go with Smart swimming pools (Separate for Adults and Children)  ‘SMARTPOOLS’ the only green certified pool product in the world !!!

The goal of this change is to create a richer experience, super hygiene, non-cumbersome & cost effective maintenance and suitable for all age groups from beginners to professionals.

VISIT WEBSITE

 

July’16 Update

final_logo_artwork


We are pleased to inform on our progress.

  • We have completed the 9th floor and 10th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 6th floor is in progress.
  • Internal electrical & plumbing works started in 3rd floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.

Referral Program

refimg


At Upscale we wish our customers, consultants, partners, vendors and friends to participate in the growth of Upscale Homes. Customer repeats and referrals have always being an integral part of our success.

Just send in the names and contact details of any acquaintance of yours who is looking to buy a home and we will get in touch with them and introduce them the world of Upscale Homes. And with each successful closure of a sale you stand to win a referral bonus check of Rs. 100,000.

REFER NOW


logo_artwork_1

June’16 Update

Last month’s progress has been the following:

  • We have completed the 8th floor and 9th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 5th floor is in progress.
  • Internal electrical & plumbing works started in 1st floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.