Nov’16 Update

final_logo_artwork


We are please to report on our progress. Details are listed below

  • Super structureCompleted
  • Brickwork Completed
  • Internal Plumbing and Electrical conduiting Completed
  • Internal Plastering – 80% completed (at 9th Floor)
  • External Plastering– 70% completed
  • Flat Flooring – 30% Completed(at 3rd Floor)
  • Corridor/Staircase Flooring – Just started
  • Internal/ExternalPainting – Just started

With this progress we are confident of flats handover for interior works may begin in April 2017 instead of June 2017.

goldenlotus-site-photo2 goldenlotus-site-photo1

Foundation Complete

We are extremely pleased to inform that Golden Lotus project foundation work is complete.


 

Current Status

  • Basement slab is in progress
    • 1/3rd of the slab is done 10days back.
    •  Another 1/3rd of the slab is going to be casted on this Wednesday i.e. 4th Nov.
    • Last 1/3rd portion will be done by 15th Nov.
  • Stilt slab works will start parallely soon.

 

Overall Status:

Even though we have some delays initially due to heavy rains, we are                     hopeful of covering up and meeting the timelines.

 

Cheers,

Upscale Homes