We are please to report on our progress. Details are listed below
- Super structure –Completed
- Brickwork – Completed
- Internal Plumbing and Electrical conduiting – Completed
- Internal Plastering – 80% completed (at 9th Floor)
- External Plastering– 70% completed
- Flat Flooring – 30% Completed(at 3rd Floor)
- Corridor/Staircase Flooring – Just started
- Internal/ExternalPainting – Just started
With this progress we are confident of flats handover for interior works may begin in April 2017 instead of June 2017.