Nov’16 Update

final_logo_artwork


We are please to report on our progress. Details are listed below

  • Super structureCompleted
  • Brickwork Completed
  • Internal Plumbing and Electrical conduiting Completed
  • Internal Plastering – 80% completed (at 9th Floor)
  • External Plastering– 70% completed
  • Flat Flooring – 30% Completed(at 3rd Floor)
  • Corridor/Staircase Flooring – Just started
  • Internal/ExternalPainting – Just started

With this progress we are confident of flats handover for interior works may begin in April 2017 instead of June 2017.

goldenlotus-site-photo2 goldenlotus-site-photo1

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s