June’16 Update

Last month’s progress has been the following:

  • We have completed the 8th floor and 9th floor slab work is in progress. Site photo is enclosed.
  • Brick work in 5th floor is in progress.
  • Internal electrical & plumbing works started in 1st floor.
  • Internal & External plastering works are in progress.
  • STP civil infrastructure is over.